The Postpone Jobs window lets you postpone the start dates or due dates for a group of jobs in a single step.
This window will change the start
dates or due dates for the jobs you've selected
in the Production Planner. All of the jobs you've
selected will get the same start date or due date,
so it should only be used to postpone a set of
jobs which are probably related.
To postpone a group of jobs
1 Choose Production > Production Planner.
2 Select the jobs you wish to change then click the postpone button.
The Postpone Job Tickets window opens, prompting you to choose a new start
date or due date and an optional production status.
3 Choose either due date or start date by clicking on the
button, then enter the new date.
4 If the production status code should be changed along
with the start or due date, choose a new status from the pop-up
menu.
5 Click OK.