Clients & Profits X Online User Guide |
Work In Progress
Managing work in progress -- the
jobs unbilled costs, time, and expenses -- is
completely automatic. There are three ways to look at
work in progress: from jobs and tasks, from the costs
themselves, and from the general ledger. Each has
important distinctions, and all three work together to
track your billable costs. Anyone with access to costs
can edit work in progress.
Work in progress is primarily a function of job billing.
Adding costs starts the work in progress system. A cost, whether it is a vendor purchase, a time entry, a
check, or an out-of-pocket expense is given a job number
and a task. The costs net and gross amount (which
include your markup) are posted to a job task. Billing is
based on the job tasks unbilled amount. When you
bill a job, its tasks are copied to the invoice --
including their billable amounts. You can freely change
the invoices billing amount up or down, regardless
of the tasks actual costs. So billing isnt
literally connected to a jobs costs.
Costs track when theyre billed automatically. When
you bill a job, the tasks billing amount is applied
to its costs. The billing amount updates the oldest cost
first, then works forward through the remaining costs.
You can find a cost and see its billing information: the
invoice date, amount billed, and invoice number. For more
accurate job costing, costs can have a billing status
(e.g., unbilled, billed, or partial). Costs can be
flagged with a billing status to keep them from being
billed (e.g., on hold, unbillable). Work in progress
reports show either unbilled job tasks or costs to help
you plan your invoices better.
To see a jobs work in progress
1 From the Job Ticket window, select WIP from the View>Point pull down menu.
Costs for all of the jobs tasks are listed by task.
Only the gross amount (the amount that includes
commissions and markups) can be edited. Changing the
costs gross amount updates the tasks unbilled
amount -- which affects how much will be billed to the
client.
To verify a jobs cost billing status
The Verify shortcut verifies that the
billing amounts are correctly applied to the jobs
costs. Billing amounts are usually applied to costs when
the clients invoice is added. If jobs are
pre-billed, however, the billing amounts cant be
applied since they havent been entered yet. In this
case the jobs costs will appear as
unbilled even though the job has been
pre-billed. The solution is to use the Verify shortcut to
reapply the jobs billings to its costs. To verify
the jobs billing status, click the Verify
button.
To change a costs billing status
Every cost gets the same unbilled
status when it is posted, unless its task is unbillable.
There are standard billing statuses (e.g., Unbilled,
Unbillable, On hold, Billed, Write-off, Partial, and
Canceled) plus you can create your own. Change the
costs billing status, then press tab to save it.
Repeat these steps for other costs, then click Save.
To transfer a jobs unbilled costs
1 From the Work in Progress window, click the
Transfer Now
button.
One-click cost transfers. Clicking the Transfer Now button transfers a jobs costs to any selected job. The dialog box gives you the option to transfer net amounts only or both net and gross amounts. |
2 Enter the job number to which
these costs should be transferred.
Any open job can be chosen to get the transferred costs.
Ordinarily, the net amounts (i.e., the agencys
actual cost) stays on the original job for more accurate
job costing; only the costs gross (i.e., billable)
amount appears on the other job. Use the transfer net
amounts option to move both the costs net and gross
amounts to the other job ticket.
To write off a jobs unbilled costs
A jobs unbilled costs can be written off in a
single click. The Write-off shortcut changes the status
on the jobs unbilled costs from
unbilled to write-off. The
costs gross amounts are erased from the job ticket,
keeping it off billing worksheets and other pre-billing
reports. Writing off unbilled costs doesnt affect
the General Ledger, since it was already updated when the
costs were posted. To write off the jobs remaining
unbilled costs, click the Write off button.
To instantly bill a jobs unbilled costs
A jobs remaining unbilled costs can be instantly
billed by clicking the Bill Now button. The Bill Now
function creates a Progress/Final invoice for the
jobs unbilled costs. The invoice is unposted, so it
can be proofed and posted like other invoices. To bill
the job, click the Bill Now button.
To print the job's work in progress
Click the Print button to print the information in the work in progress window.